
Catching that view of the “traffic calming feature” taking shape at 63rd/Alki last weekend, we thought it was time to check on progress of the Alki Point sidewalk project that it’s part of, now that construction’s been under way for two months. Here’s the progress report we procured from SDOT’s Therese Casper:
Construction of the sidewalk along Alki Ave SW has been progressing. However, it has been slower than originally anticipated due to utility relocations including a gas line and utility replacement including a portion of the existing storm drain at the southern end of the project area. In addition, water meter adjustments took longer than expected.
The raised crosswalk at the eastern end of the project area is complete as well as the sidewalk to Point Place SW. The remaining sidewalk will be poured Thursday and Friday. All major elements should be complete by early June with a few locations remaining in construction as final utility work is done.
The project was initiated as part of the Neighborhood Street Fund, and drew some controversy in the neighborhood after it finally won a grant, mostly out of concerns that many waterfront residences would lose parking, but SDOT came up with a plan that in the end took away far fewer spaces than originally feared (here’s our report on the pre-construction project-site tour in February, with more information on the project’s scope).
| 8 COMMENTS